NORCAT |
DATE: |
January 26 & 27,
1999 |
|||||||||||||||||||||||||||||
| ROCK BOLT
TYPE: |
Skema Friction
Stabilizers |
||||||||||||||||||||||||||||||
| IN ATTENDANCE: |
Bill Quesnel, Len
Leblanc - PHQ Eric Nelson Consultant Mark Poulin, Doug Luhta, Mike Mooney - NORCAT |
||||||||||||||||||||||||||||||
| PURPOSE |
Installation,
pull
test and removal of Skema split tube assemblies. |
||||||||||||||||||||||||||||||
| LOCATION |
NORCAT Underground
Centre, Onaping, Ontario |
||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||
1. Holes were drilled by jackleg (115 psi drill pressure). Installation of split set tubes was also by jackleg using generic style driver tool. This caused some flaring of ring ends & loss of impact energy. |
|||||||||||||||||||||||||||||||
| 2.
Pull tests were conducted using Enerpac RCH 302 center hole jack and claw style pull
assembly.
Instructions
Hydraulic Rock Bolt Tester PDF
|
|||||||||||||||||||||||||||||||
| 3. Tubes #1 & #5 were marked & removed for NORCAT corrosion testing | |||||||||||||||||||||||||||||||
Send mail to webmaster@partshq.com
with questions or comments about this web site or travel to Reach
Us.
Copyright © 1997 Parts HeadQuarters Inc. All
rights reserved. Information in this document is subject to change without notice.
Other products and companies referred to herein are trademarks or registered trademarks of
their respective companies or mark holders.
Last modified:
November 07, 2007